Odisha govt pushes to clear final land hurdles for Talcher-Bimalagarh rail line

Odisha govt convened a review meeting to accelerate land acquisition for the long‑delayed Talcher‑Bimalagarh broad‑gauge railway line.

25 August 20262 min read
Odisha govt pushes to clear final land hurdles for Talcher-Bimalagarh rail line
Image: via source article

On August 22, 2026, Odisha’s Additional Chief Secretary of Revenue and Disaster Management, Dr Arabinda Kumar Padhi, chaired a review meeting at Loka Seva Bhawan in Bhubaneswar to expedite land acquisition for the Talcher‑Bimalagarh new broad‑gauge railway line. The project, sanctioned in the 2003‑04 railway budget, remains incomplete after more than two decades, with a final stretch of land still pending before construction can resume.

How much land remains to be acquired and what types?

Of the total 2,144.028 acres required for the 149.78‑km line, 1,868.357 acres have already been acquired, leaving 275.671 acres yet to be secured. This pending parcel comprises 202.15 acres of private land, 13.7 acres of forest land and 59.821 acres of government land.

What steps were discussed to speed up land acquisition?

The review meeting covered the status of remaining land acquisition, compensation to affected landowners, cases pending in court, and the handover of land already acquired to the railways. Dr Arabinda Kumar Padhi emphasized that public interest must come first and said, “Public interest must come first. Remaining land must be acquired and transferred free of obstacles without further delay so that construction can move at full speed.” Attendees included Railway Coordination Commissioner Kaustuv Dipta Pani, Deogarh District Collector Kabindra Kumar Sahu, Presiding Officer Abhijit Palei and other senior officials. The meeting also covered the status of compensation for affected landowners. The officials also examined the pending court cases related to land acquisition.

Why has the Talcher‑Bimalagarh line faced delays and what benefits are expected?

The Talcher‑Bimalagarh broad‑gauge line was first approved in the 2003‑04 railway budget and is designed to shorten the Rourkela‑Talcher route by approximately 126 kilometres once completed. In addition to reducing travel distance, the line is intended to open rail connectivity in relatively underdeveloped stretches of Angul, Deogarh and Sundargarh districts. Over the past twenty years the project has repeatedly missed its scheduled deadlines, chiefly because of land acquisition disputes and the ensuing litigation that has stalled work on the final land parcel.

Frequently asked

What is the total length of the Talcher‑Bimalagarh railway line?

The line is 149.78 km long.

How much land has been acquired for the project so far?

1,868.357 acres of the required 2,144.028 acres have been acquired.

How much land remains to be acquired and what types?

275.671 acres remain pending, comprising 202.15 acres of private land, 13.7 acres of forest land and 59.821 acres of government land.

Who chaired the review meeting on land acquisition for the Talcher‑Bimalagarh line?

Dr Arabinda Kumar Padhi, Additional Chief Secretary of the Revenue and Disaster Management Department, chaired the meeting.

What did Dr Arabinda Kumar Padhi say about the pending land acquisition?

He said, “Public interest must come first. Remaining land must be acquired and transferred free of obstacles without further delay so that construction can move at full speed.”

Which districts will benefit from the completed Talcher‑Bimalagarh railway line?

The line will improve connectivity in Angul, Deogarh and Sundargarh districts.

Manisha Naik
Sundargarh Correspondent

Manisha Naik

District Correspondent, Deogarh

Manisha Naik covers Deogarh's forest and wildlife beat, rural development, and local governance, reporting from the district headquarters.

View all articles by Manisha
Share this article
Discussion
By posting you agree to our Terms & Privacy.

Loading…